Weekly Roadwork Report
Bowie County
I-30 – From FM 989 to AR State Line, reconstructing and widening highway, daytime work in median. Motorists should watch for trucks and equipment pulling onto the interstate
I-30 – At Exit 207/Spur 594 westbound, ramp rehabilitation. Exit ramp to be closed. I-30 westbound lanes in this area restricted to one lane
SH 8 – At Sulphur River, replacing bridges
SH 98 – At Anderson Creek, bridge replacement. Traffic restricted to one lane with signal lights controlling traffic through work zone
Cass County
SH 8 – At Sulphur River, replacing bridges
US 67 – Widening bridge at Jennings Slough. Signal lights controlling one-way traffic
Harrison County
I-20 – At US 59 overpass, replacing bridge. US 59 traffic shifted to southbound lanes
I-20 – Concrete pavement repair. Various daytime lane closures, expect delays
I-20 – At Lansing Switch Road, constructing new bridge over interstate. Lansing Switch Road closed to through traffic. Possible lane closures on I-20
SH 43 – At Kansas City Southern Railroad in Karnack, widening bridge over railroad. Northbound lanes closed with signal lights controlling one-way traffic
US 80 – From Loop 390 to Interstate 20, resurfacing highway. Daytime lane closures, expect delays
Marion County
US 59 – From SH 49 to two miles north of SH 49, repairing and resurfacing highway. Lane closures, expect delays
US 59 – From Cass County line to 2 miles north of SH 49, installing safety barrier cable. Daily lane closures
Editor’s note: This is a schedule of work being planned for the dates noted above. Weather conditions and unforeseen problems can cause delays or cancelation of work. For more information about construction projects, contact Heather Deaton, Public Information Officer, TxDOT Atlanta District, 903-799-1306, Heather.Deaton@TxDot.gov