I-30 – From FM 989 to AR State Line, reconstructing and widening highway, daytime work in median. Motorists should watch for trucks and equipment pulling onto the interstate

SH 8 – At Sulphur River, replacing bridges

SH 98 – At Anderson Creek, bridge replacement. Traffic restricted to one lane with signal lights controlling traffic through work zone

Cass County

SH 8 – At Sulphur River, replacing bridges

US 67 – Widening bridge at Jennings Slough. Signal lights controlling one-way traffic

Upshur County

US 271 – From 5.9 miles north of SH 155 to 1.5 miles north of SH 155. Resurfacing highway

Editor’s note: This is a schedule of work being planned for the dates noted above. Weather conditions and unforeseen problems can cause delays or cancellation of work. For more information about construction projects, contact Heather Deaton, Public Information Officer, TxDOT Atlanta District, 903-799-1306, Heather.Deaton@TxDot.gov